Installing The Seven-core Cable For A Submersible Mixer Requires Professional Operation.

Installing a submersible mixer's seven-core cable requires professional operation.

The following are key steps and precautions:

I. Wiring Method
The seven-core cable includes:

Three-core thick wire: Three-phase live wire (L1/L2/L3)

Yellow/green dual-color wire: Ground wire (PE)

Wire #31: Motor leakage signal wire

Wires #11 and #12: Motor overheat protection signal wires

II. Installation Points

Cable Protection: Use dedicated fixing rings (spacing ≤80cm) to secure the cable and prevent tangling.

Sealing Treatment: Inject dedicated sealant (such as 3M Scotchcast 2131) into the wiring cavity to ensure waterproof performance.

Double Protection: Install an underwater cable entry sealing auxiliary mechanism and a surface anti-fall device.

III. Safety Specifications
During hoisting, the impeller end should be tilted upwards by 5°-10° to maintain a vertical center of gravity.

Forced hoisting is strictly prohibited. If jammed, gently shake the chain.

After wiring, use a megohmmeter to test the insulation resistance (≥50MΩ).